Tata Semiconductor Plant in Dholera: Latest Status and 2026 Updates
October 22, 2026

Table of Contents
The Tata Semiconductor Plant in Dholera SIR region is a major semiconductor manufacturing project in Gujarat. With a investment of ₹91,000 crore, the project aims to strengthen India's chip manufacturing industry. The facility is being developed by Tata Semiconductor Manufacturing, with technology support from Taiwan's Powerchip Semiconductor Manufacturing Corporation (PSMC).
On 16 October 2026, Gujarat Chief Minister Bhupendra Patel reviewed construction progress at the Tata semiconductor plant during his visit to Dholera Special Investment Region (SIR). The visit also covered industrial development, public facilities and connectivity projects across the region.
Tata Semiconductor Plant Dholera: Key Facts
| Detail | Information |
|---|---|
| Location | Dholera SIR, Gujarat |
| Proposed investment | ₹91,000 crore |
| Company | Tata Semiconductor Manufacturing |
| Technology partner | PSMC, Taiwan |
| Planned capacity | 50,000 wafer starts per month |
| Wafer size | 300 mm |
| Expected employment | 21,000 direct and indirect jobs, as projected in the SEZ notification |
What is the Current Status of the Tata Semiconductor Plant in Dholera?
The Tata Electronics Dholera fab is being developed as a semiconductor fabrication facility and is reported to be around 50% complete. In April 2026, the government notified a 66.166-hectare Special Economic Zone (SEZ) for the project.
In May 2026, Tata Electronics announced a partnership with ASML to support the fab with lithography equipment, technical solutions, local skill development and research infrastructure.
The project is expected to begin trial chip production in December 2026. However, this is a target and does not mean that trial production has already started.
What Chips Will the Dholera Semiconductor Plant Make?

The planned fab is designed to manufacture chips using 300 mm wafers and process technologies in the 28-110 nanometre range, according to project information. These chips can support industries such as automotive, communications, computing and power management.
The facility is expected to help build India's domestic semiconductor manufacturing capacity and reduce reliance on imported chips over time.
How Many Jobs Will the Tata Semiconductor Project Create?
The government’s SEZ notification lists 21,000 expected jobs, including direct and indirect employment. These are projected opportunities, not jobs already created.
The project may also support demand for skilled engineers, technicians, equipment specialists and other workers across the semiconductor supply chain as development progresses.
How Could the Tata Project Affect Dholera?
The Tata semiconductor project could support industrial growth, job creation and demand for supporting infrastructure in Dholera SIR. As the plant develops, it may attract semiconductor suppliers, technology companies and other businesses to the region.
Along with the Dholera International Airport, Ahmedabad–Dholera Expressway and other infrastructure projects, the plant could contribute to the wider development of Dholera Smart City.
FAQs
1. Is the Tata semiconductor plant in Dholera operational?
As of October 2026, the plant is under development. Commercial production has not been confirmed.
2. What is the investment in the Tata semiconductor project?
The proposed investment is ₹91,000 crore.
3. Who is the technology partner for the Dholera fab?
PSMC is the technology partner, while ASML has announced a partnership to support lithography systems and related capabilities.
4. When is commercial production expected to begin?
Recent reporting points to mid-2028, but the timeline remains a target and may change.
5. How many jobs are expected from the project?
The government’s SEZ notification lists 21,000 proposed direct and indirect jobs.